Future Districts

Future Underground Utility Districts
The following is a prioritized list of streets for future Underground Utility Districts, which was approved by City Council on August 14, 2007.
  • Orien Avenue - From 7447 Orien Avenue to 7485 Orien Avenue - COMPLETED
  • Normal Avenue - From Lowell Street to La Mesa Boulevard - COMPLETED (to Windsor)
  • Massachusetts Avenue - From University Avenue to Waite Drive - Under design
  • Waite Drive - From Murray Hill Road to 69th Street/city limits - Under design
  • Lowell Street - From University Avenue to Orien Avenue
  • Parks Avenue - From University Avenue to Normal Avenue
  • Lemon Avenue - From Grant Street to Bancroft Drive
  • Dallas Street - From Lake Murray Boulevard to Fletcher Parkway Drive
  • 70th Street - From University Avenue to Colony Road/city limits
  • Lake Murray Boulevard - From Aztec Drive to Dallas Street/city limits